Skip to article

Phantom permits

121,000 approvals that never broke ground


Summary

Of the 161,135 planning applications ever approved (PA route, "Grant Permission"), only 40,096 — just 24.9% — have a recorded commencement date. The remaining 121,039 permits are phantoms: approved by the planning system but never officially commenced. Even focusing on recent years where data is more reliable, roughly 1 in 4 approved permits from 2015–2022 were never acted on. Malta's planning system is not just deciding what gets built — it's producing a vast surplus of theoretical development that never materialises.

Key findings

Commencement rates by year

Year filed Approved Commenced Commenced %
2010 4,150 217 5.2%
2012 3,109 245 7.9%
2014 3,709 883 23.8%
2015 4,721 2,599 55.1%
2016 5,653 4,416 78.1%
2017 6,007 4,757 79.2%
2018 6,070 4,672 77.0%
2019 5,534 4,277 77.3%
2020 5,182 3,893 75.1%
2021 5,801 4,209 72.6%
2022 4,968 3,308 66.6%
2023 4,876 2,812 57.7%

Commencement tracking appears to have become reliable from around 2015 onwards (pre-2015 rates are implausibly low, likely reflecting incomplete data). Even in the best years (2016–2017), roughly 1 in 5 approved permits were never commenced. By 2022, the uncommenced rate had risen to 1 in 3.

The 2023 figure (57.7%) likely reflects a lag — permits filed in 2023 may still be within their validity period. But the declining trend from 2017's 79.2% to 2022's 66.6% is notable even accounting for this.

Phantom permits by project type (2015–2020)

Category Approved Not commenced Phantom rate
Offices 1,285 435 33.9%
Shops/Retail 1,507 486 32.2%
Sanctioning (other) 4,678 1,345 28.8%
Restaurants 308 86 27.9%
Other 10,241 2,820 27.5%
Garages 4,960 1,269 25.6%
Hotels 262 65 24.8%
Dwellings 3,080 726 23.6%
Pools 1,543 329 21.3%
Apartments 5,224 971 18.6%

Offices and retail have the highest phantom rates — roughly one in three approved office or shop permits are never commenced. This likely reflects speculative applications: developers securing permission to test the market, or property owners obtaining permits to increase their land's paper value without intending to build.

Apartments have the lowest phantom rate (18.6%), suggesting that when someone gets permission to build apartments, they're more likely to actually do it — consistent with Malta's strong housing demand.

Sanctioning permits: built but never "commenced"

A curious finding: 28.8% of sanctioning permits — which legalize already-built structures — have no commencement date. The building already exists, yet the permit was never formally commenced. This suggests either an administrative gap in tracking, or applicants who obtained the sanctioning permit but never followed through with the final compliance steps.

By application type

Application type Approved Commenced Commenced %
Outline development permission 303 5 1.7%
Renewal of development permission 1,251 434 34.7%
Amended development permission 258 150 58.1%
Full development permission 54,834 37,386 68.2%

Outline permissions are almost never commenced (1.7%) — which makes sense, as they're preliminary approvals that require a full application before construction begins. But the 65.3% uncommenced rate for renewals is striking: two-thirds of renewed permits are never acted on, suggesting developers are hoarding permits by renewing them repeatedly without building.

ODZ vs WDZ: no difference

Zone Approved Commenced %
Outside Development Zone 9,608 67.1%
Within Development Zone 47,040 67.0%

Surprisingly, the commencement rate is virtually identical whether the project is inside or outside the development zone. ODZ permits — which are harder to obtain — are no more likely to actually be built.

Architects with the highest phantom rates (200+ permits, 2015–2022)

Architect Approved Uncommenced Phantom %
Perit Cornelia Tabone 267 135 50.6%
Dr Edwin Mintoff 596 229 38.4%
Perit Stephen Farrugia 218 81 37.2%
Perit Chris Cachia 535 184 34.4%
Perit David Vassallo 228 78 34.2%
Perit Joseph Attard 255 86 33.7%
Perit Gilbert Bartolo 259 83 32.0%
Perit Elena Borg Costanzi 211 67 31.8%
Falzon & Cutajar 993 314 31.6%
Perit Paul Camilleri 301 94 31.2%

One architect has a 50.6% phantom rate — more than half the permits they obtain are never commenced. Falzon & Cutajar, one of Malta's most prolific firms (993 approved permits in this period), has a 31.6% phantom rate — 314 approved projects that never broke ground.

Why this matters

Phantom permits represent a hidden cost to Malta's planning system. Every application that goes through the full assessment process — case officer review, public consultation, board hearing — consumes administrative resources. When a quarter or more of approved permits are never used, it means the planning system is doing significant work for developments that will never exist. More importantly, phantom permits can be used strategically: to inflate property values, to block competing developments on adjacent sites, or to "bank" development rights for future use. The system assesses each application as if it will be built, but the data shows that many are speculative from the start.

Ask the Data

Explore 291,197 planning cases from 1993–2026

Try asking