Skip to article

Thirty-one thousand same-day decisions

Planning at industrial speed

System

Summary

The Malta Planning Authority decided 31,533 planning applications on the same day they were received — and a further 27,535 within the first week, for a total of 59,068 cases (25.2% of the entire database) resolved in seven days or fewer. Some of these are legitimate fast-tracks for minor works. But the sheer scale — one in four planning applications in Malta's history decided within a week — raises questions about the depth of assessment possible in that timeframe. Paradoxically, these ultra-fast decisions have a lower approval rate than slower ones, suggesting the speed isn't a sign of rubber-stamping but of a two-tier system where simple cases are processed at industrial speed.

Key findings

The speed distribution of 233,916 decided cases

Processing time Cases % of total Approval rate
Same day (0 days) 31,533 13.5% 60.5%
1–7 days 27,535 11.8% 70.2%
8–30 days 55,769 23.8% 69.1%
31–90 days 72,452 31.0% 84.4%
91–180 days 37,221 15.9% 85.6%
181–365 days 7,862 3.4% 81.0%
1–2 years 1,168 0.5% 74.3%
2–5 years 336 0.1% 68.2%
5+ years 40 0.02% 77.5%

The sweet spot for applicants is 91–180 days: cases in this range have an 85.6% approval rate. Same-day decisions have the lowest approval rate at 60.5%.

The speed paradox

Conventional wisdom holds that fast decisions indicate a rubber stamp. This data tells the opposite story:

Speed category Approval rate
Fastest (0–7 days) 65.0%
Medium (31–180 days) 84.8%
Slowest (1–5 years) 72.3%

Cases that take the longest appear to be contested or complex, dragging down their approval rate. But the truly surprising finding is that the fastest quarter of all cases has the lowest approval rate in the entire distribution. This likely reflects a high proportion of "not accepted" or procedurally rejected cases among same-day decisions — applications that fail at the front door.

Same-day decisions: what happens to them?

Of the 31,533 same-day decisions:

Outcome Cases %
Approved/Granted 19,078 60.5%
Refused 2,216 7.0%
Other (accepted, not accepted, withdrawn, etc.) 10,239 32.5%

The "other" category likely includes administrative decisions — applications accepted or rejected on procedural grounds before substantive review.

Speed has changed dramatically over time

Average processing time, by era:

Period Avg days to decision Cases/year
1994–2001 33 days 6,877
2002–2010 24 days 8,040
2011–2018 89 days 7,316
2019–2024 84 days 6,081

Processing times tripled between the early 2000s and the 2010s. The fastest year was 2002 at just 13 days average (during a volume surge to 9,552 cases). The slowest was 2023 at 103 days. The system got dramatically slower even as it became dramatically more permissive — suggesting it was doing more procedural work per case while simultaneously approving nearly everything.

The 28-year case

The longest case in the database took 10,270 days — 28.1 years — from reception to validation. Forty cases exceeded five years. These extreme outliers likely represent legacy applications that were administratively closed long after their original filing.

Why this matters

A planning system that decides 13.5% of its cases on the day they arrive and takes an average of 89 days for the rest is operating as two different institutions. The fast track processes straightforward applications (DN cases, minor notifications) at conveyor-belt speed. The standard track takes three months and approves at 85%. The result is a system where the speed of your decision depends not on how carefully your application is assessed, but on which category it falls into — a structural inequality baked into the process itself.

Ask the Data

Explore 291,197 planning cases from 1993–2026

Try asking